| Florida Engineering and Design
was retained to design a wastewater collection system
to replace septic tanks located in Crandon Park,
Key Biscayne (Miami, FL). The sewer system engineering
and design included gravity pipeline layout and
sizing and lift stations design. FED has an in-house
design and graphics staff that produced drawings
for the client to use in soliciting the project
construction bids.
This project required sanitary system design
and documents for construction including gravity
sewer, force main, manholes, pump stations, sewer
laterals and plumbing, pavement restoration specifications,
septic tanks and associated drain fields abandonment,
electrical connections, site clearing, testing,
sod restoration and mitigation design for impacts
to environmentally sensitive areas. This park
includes a golf course, rest room facilities,
international tennis court complex, snack bar,
etc. The requirements of the sanitary sewer lift
stations were such that there was excess capacity
included in the system for future expansion. This
resulted in the need for multiple alternatives
to be presented with present worth calculations
and reviewed by the city prior to the finalization
of plans. Miami/Dade Parks and Recreation Department
own this project site.

|